Hi

Basically the link between costcenter and the activity type is maintain in KP26 transaction code , this T.code belongs to FI/CO module. So ask your CO consultant to assign the new activity type to the particular cost center.

Otherwise if you access for the T code KP26

Enter Version = 0

From period = enter from which period you want to enter for example 5

To period = for example 7

Enter the cost center

and enter the activity type

press enter

in the table you enter the fixed price of the activity and save.

Please try and come back