8. Click Copy (Shift+F9) ****on.
Information: When the copied record is displayed, make the necessary changes to the record. In this example, date type NR is added to the record and the validity dates are changed to reflect the current day through 12/31/9999.
Copy Date Specifications
9. Update the following required and optional fields:
Field Name | Description | R/O/C | Values | Start
| Beginning date of the specified date range
| R | Enter value in Start.
Example: 04/20/07
| Date type
| Code identifying the format for the date followed by schedule dates
| R | Enter value in Date type.
Example: NR
| NR
| | R | Enter value in NR.
Example: 06/15/2007
|
10. Press ENTER.
11. Click Save (Ctrl+S) ****on.