How do we configure the following 2 scenarios:


(1) Period work schedule for 2nd and Last Saturday Off and all Sundays Off.
(2) Period work schedule for 2nd and 4th Saturday Off and all Sundays Off.



ANS:1 Same solution is there for both of your threads.


All Sundays off : Create a daily work schedule OFF with planned working hours 0. and assign the same in period work schedule in the last field as it denotes Sunday.


2nd Saturday off : Go to Public Holiday Calendar in time management work schedules


Then create public holiday
Select " With a fixed day from date ".
Select Saturday
Enter "8" in day field.
Enter "1" in month field.
Save the Holiday.
Assign the holiday to the holiday calendar.
Assign the holiday Calendar to Factory Calendar.


In Factory Calendar, tick all the days except Sunday.


Go to display calendar.
It will display the second saturday as off in your calendar for January Month.
If you want to create for all the months, repeat the above process by giving 2,3,4,5,6........12 in the month field.
So that it will show all second saturdays as offs in your calendar.
4th or Last Saturday :


Repeat the above process by giving 21 in the day field and month numbers in the month field.


Another process is also there with the help of "Special days" concept. But the result will be the same.


Thats why go ahead with the above process.
100% you will get the solution.